Critical Thinking Questions Case 2 in Your Work in the IT

Question 130

Multiple Choice

Critical Thinking Questions Case 2 In your work in the IT department, you are charged with asking the difficult questions about the feasibility of new systems as they are being develope d. Knowing that you are an expert on feasibility assessment, a colleague has come to you for advice on an issue of schedule feasibility. His project deadline has been adjusted twice before and cannot be extended again. What is an option for him?


A) Creating a new schedule
B) Reducing the project scope
C) Increasing the project creep
D) Performing a payback analysis

Correct Answer: