Che contracted with a software development team to create a program for his company.He wants to review the budget and schedule for the project every week.Which project team member should he contact for this information?
A) IT department
B) Designer
C) Project manager
D) Programmer
Correct Answer:

Verified
Correct Answer:
Verified