A Logistics Manager Is Developing a Supply Chain Risk Management

Question 20

Multiple Choice

A logistics manager is developing a supply chain risk management plan incorporating contingency plans for alternatives to transport failures. Which of the following factors best represents this approach?


A) Avoidance
B) Acceptance
C) Mitigation
D) Redundancy

Correct Answer: