Multiple Choice
Reducing set up time will affect item lead time and throughput in which of the following ways?
A) Lead time will increase, throughput will decrease
B) Lead time will increase, throughput will increase
C) Lead time will decrease, throughput will increase
D) Lead time will decrease, throughput will decrease
Correct Answer:

Verified
Correct Answer:
Verified