Multiple Choice
Which is an objective of the Managing Product Delivery process?
A) Sign-off completed Work Packages
B) Ensure the Business Case is kept under review
C) Report progress to the Project Board
D) Ensure that work on products is authorized and agreed with the team
Correct Answer:

Verified
Correct Answer:
Verified