Multiple Choice
Which statement about risks is FALSE?
A) A risk that could have a positive impact on a project's objectives is known as an opportunity
B) A risk that could have a negative impact on a project's objectives is known as a threat
C) A risk that a project's product is incomplete is known as an off-specification
D) A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
Correct Answer:

Verified
Correct Answer:
Verified