Multiple Choice
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?
A) Corporate management
B) Project Board
C) Project Assurance
D) Project Manager
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q108: Which is a purpose of the Project
Q109: Which is a purpose of a Project
Q110: Which role is part of the project
Q111: Which product documents the information needed to
Q112: Which is NOT a purpose of a
Q114: Which is one of the six aspects
Q115: Identify the missing word(s) in the following
Q116: Which process is used by a Team
Q117: Which risk response type is a recommended
Q118: Where should a Team Manager look for