Identify the Missing Words in the Following Sentence

Question 96

Multiple Choice

Identify the missing words in the following sentence. When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.


A) Configuration Item Records
B) Business Case
C) Project Brief
D) project management team and/or role descriptions

Correct Answer:

verifed

Verified