Multiple Choice
Which describes a risk effect?
A) The uncertainty expressed as a negative or favourable occurrence
B) The issue which is affecting the project and has resulted in a risk
C) The impact(s) on the project objectives should the threat or opportunity occur
D) The change in the status of a risk in response to actions taken to control it
Correct Answer:

Verified
Correct Answer:
Verified