Question 3

Multiple Choice

A project, which was initiated several months ago, has been impacted by the following changes: 1. An organizational restructure has altered the responsibilities of the stakeholders. 2. A new chief executive has been appointed, who has new ideas regarding the immediate focus of the project. Which of the following attributes in a requirements catalogue entry would need to be updated to reflect these changes?


A) Owner, source.
B) Priority, owner, version history.
C) Rationale, priority, source.
D) Version history, author, rationale.