Multiple Choice
A project, which was initiated several months ago, has been impacted by the following changes: 1. An organizational restructure has altered the responsibilities of the stakeholders. 2. A new chief executive has been appointed, who has new ideas regarding the immediate focus of the project. Which of the following attributes in a requirements catalogue entry would need to be updated to reflect these changes?
A) Owner, source.
B) Priority, owner, version history.
C) Rationale, priority, source.
D) Version history, author, rationale.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Peter is analyzing requirements elicited for a
Q2: An inexperienced business analyst has been asked
Q4: A business analyst is allocating elicited requirements
Q5: Below are statements about what a use
Q6: A business analyst is working on a
Q7: A business analyst is concerned that the
Q8: A business analyst is in the process
Q9: An international travel operator has a customer
Q10: In developing requirements, a business analyst has
Q11: An automated software tool is being used