Multiple Choice
A Citrix Engineer needs to return an environment back to normal operations after a Disaster Recovery (DR) occurred. Which two tasks does Citrix recommend to move the users from the backup datacenter to the primary datacenter? (Choose two.)
A) Terminate existing user sessions.
B) Block access to the Disaster Recovery datacenter.
C) Enable access to the primary datacenter.
D) Block access to the primary datacenter.
E) Enable access to the Disaster Recovery datacenter.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which database high availability option does Citrix
Q3: Which file is used to store a
Q4: Scenario: A Citrix Engineer is working on
Q5: A SQL Database Administrator has been asked
Q6: Scenario: A Citrix Engineer needs to use
Q7: Scenario: A Citrix Engineer created four application
Q8: Scenario: A Citrix Engineer is maintaining a
Q9: Which two statements are valid regarding communication
Q10: How often should a Citrix Engineer backup
Q11: What are two valid Redundancy options for