Question 70

Multiple Choice

Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A. What is the opportunity cost in this scenario?


A) $331013
B) There is not enough information to know as the risk for Project B has not been quantified.
C) $235,987
D) $567,000