Multiple Choice
Which of the following process models needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle?
A) Procedural model
B) Evolutionary model
C) Spiral model
D) Waterfall model
Correct Answer:

Verified
Correct Answer: