Multiple Choice
A company is in the middle of a large-scale project. Safety concerns have been brought up by several stakeholders, and this has led to numerous proposed changes. The business analyst (BA) must now assess the impact that marking these changes will have on the project. When assessing the impact of safety concerns, which of the following should be considered?
A) Cost/benefit analysis
B) Urgency
C) Risk register
D) Design