You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?
A) RAM Chart
B) Affinity Diagram
C) Stakeholder Analysis
D) Text-Oriented Chart
Correct Answer:

Verified
Correct Answer:
Verified