A System Owner Calls the Project Team to Inquire About

Question 254

Multiple Choice

A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?


A) Record a defect for fixing
B) Consult with the project manager
C) Revert back the changes
D) Check the audit history of changes