Multiple Choice
You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?
A) Project schedule
B) Project scope management plan
C) Project reporting structure
D) Project communications management plan
Correct Answer:

Verified
Correct Answer:
Verified