Multiple Choice
When decomposing stories, the concept of "breadth before depth" signifies progressively breaking down:
A) Estimates and resources required to accomplish the story
B) Backlog items to the lowest level of detail upfront
C) Business goals into user stories representing smaller increments of value
D) Tests to align with usable functionality delivered through each story
Correct Answer:

Verified
Correct Answer:
Verified