During a Delivery Team Meeting, Some Members of the Team

Question 3

Multiple Choice

During a delivery team meeting, some members of the team are confused about the "time" dimension depicted on a story map. After some discussion they conclude it describes:


A) User story implementation order
B) The project timeline
C) Sequence of activities a user follows
D) Time to complete stories

Correct Answer: