Multiple Choice
Wanting to ensure the delivery team is working as productively as possible, they decide backlog items, including user stories, should be:
A) Fully detailed before they get prioritized
B) Refined and elaborated by the Tech Lead
C) Refined and elaborated throughout the planning horizons
D) Fully detailed as they enter the backlog