Elizabeth is considering how to structure a project team that will not directly disrupt ongoing operations.The project needs to be done quickly and a high level of motivation will be needed in order to do that.For this situation, the ______ organization would be the best choice.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Projectized
Correct Answer: