Which of the Following Represents the Correct Order of the Risk

Question 420

Multiple Choice

Which of the following represents the correct order of the risk management process?


A) Resource allocation, risk management metrics, risk assessment, post-mortem analysis, effective communication.
B) Risk management metrics, resource allocation, risk assessment, effective communication, post-mortem analysis.
C) Risk assessment, resource allocation, risk governance and reporting, post-mortem analysis, feedback.
D) Resource allocation, risk monitoring, risk assessment, feedback, post-mortem analysis.

Correct Answer: