After Completing a Net Present Value (NPV) Calculation on a Proposed

Question 336

Multiple Choice

After completing a net present value (NPV) calculation on a proposed project, an analyst explores the change in NPV with changes in the interest rate. This additional analysis is referred to as:


A) Decision analysis.
B) Simula-tion.
C) Sensitivity analysis.
D) Variance analysis.