Which of the Following Would Be an Appropriate Outcome of a Quality

Question 49

Multiple Choice

Which of the following would be an appropriate outcome of a quality assurance and improvement program in an internal audit activity? 1. Modification of resources. 2. Corrections to procedures. 3. Changes in processes. 4. Implementation of new technology.


A) 2 and 4 only
B) 3 and 4 only
C) 1, 2, and 3 only
D) 1, 2, 3, and 4

Correct Answer:

verifed

Verified