Multiple Choice
Which is a definition of a risk cause?
A) The impact of a risk on the stage and project tolerance
B) The source of a risk
C) The overall effect of a risk on the Business Case
D) How likely a risk is to occur in a given project situation
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q65: Which is the correct explanation of the
Q66: Which one of the following is a
Q67: Access Management is closely related to which
Q68: Where should the following information be stored?
Q69: Which process or function is responsible for
Q71: Which of the following BEST describes technical
Q72: Which of the following should be documented
Q73: Which process will perform risk analysis and
Q74: Which function or process would provide staff
Q75: Third parties responsible for supplying goods or