You Are Contacting a Stakeholder Who Has a High Level

Question 20

Multiple Choice

You are contacting a stakeholder who has a high level of power but has little interest or support for the project. Which type of engagement is recommended?


A) Persuade the stakeholder.
B) Show consideration to the stakeholder.
C) Engage and consult the stakeholder regularly.
D) Meet the needs of the stakeholder.