Multiple Choice
In the level SOP strategy,variations in demand from period to period are met by
A) varying production levels by adjusting employment levels.
B) varying production levels without adjusting employment levels.
C) changing price levels.
D) using inventory buffers.
Correct Answer:

Verified
Correct Answer:
Verified