Multiple Choice
The initial step in the risk management process is to
A) Determine the level of acceptable risk.
B) Assess the risk potential.
C) Identify the risks.
D) Set aside budget funds for managing the risks.
E) Appoint a risk manager.
Correct Answer:

Verified
Correct Answer:
Verified