Multiple Choice
The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk
A) Assessment form.
B) Responsibility matrix.
C) Scenario assessment.
D) Impact assessment.
E) Severity matrix.
Correct Answer:

Verified
Correct Answer:
Verified