Short Answer
When considering risk response development, assuming the risk because the chance of such an event is slim is known as _________ the risk.
Correct Answer:

Verified
retaining
Explanation: Some risks are so...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
retaining
Explanation: Some risks are so...
Explanation: Some risks are so...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Related Questions
Q17: What is the purpose of using tools
Q59: Which of the following is NOT one
Q68: Choosing to move a concert indoors to
Q70: Adopting proven technology instead of experimental technology
Q71: Describe the relationship between the likelihood of
Q72: The event or point in time when
Q74: The likelihood of a risk event occurring
Q75: Performance bonds, warranties, and insurance are examples
Q76: The _ form identifies each risk event,
Q98: Which of the following groups should NOT