A Customer Requests a Report That Summarizes Functionality Added and Defects

Question 6

Multiple Choice

A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?


A) The Product Owner
B) The Scrum Master
C) The team
D) This type of report should not be prepared.

Correct Answer: