Multiple Choice
What do acceptance criteria identify?
A) The approach that will be used to prove whether the project's products have been completed
B) A measureable improvement resulting from a project outcome
C) The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
D) The project controls set up during the process Initiating a Project
Correct Answer:

Verified
Correct Answer:
Verified