After multiple service interruptions caused by an older datacenter design, a company decided to migrate away from its datacenter. The company has successfully completed the migration of all datacenter servers and services to a cloud provider. The migration project includes the following phases: Selection of a cloud provider Architectural design Microservice segmentation Virtual private cloud Geographic service redundancy Service migration The Chief Information Security Officer (CISO) is still concerned with the availability requirements of critical company applications. Which of the following should the company implement NEXT?
A) Multicloud solution
B) Single-tenancy private cloud
C) Hybrid cloud solution
D) Cloud access security broker
Correct Answer:

Verified
Correct Answer:
Verified
Q338: An organization is implementing a virtualized thin-client
Q339: A Chief Information Security Officer (CISO) recently
Q340: Users have been reporting unusual automated phone
Q341: A network service on a production system
Q342: Given the following code snippet: <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg"
Q344: A security administrator is concerned about the
Q345: A large, public university has recently been
Q346: The government is concerned with remote military
Q347: Company leadership believes employees are experiencing an
Q348: While investigating suspicious activity on a server,