A company is migrating a legacy application to the cloud. Two C-level executives are currently engaged in the initial stages of the migration, and they are planning a rip-and-replace approach. Before initiating the project, the FIRST step should be to identify:
A) the required network performance.
B) the key stakeholders.
C) the desired CSP.
D) the required cloud services.
E) the required amount of storage.
Correct Answer: