Multiple Choice
A company just successfully completed a DR test and is ready to shut down its DR site and resume normal operations. Which of the following actions should the cloud administrator take FIRST?
A) Initiate a failover.
B) Restore backups.
C) Configure the network.
D) Perform a failback.
Correct Answer:

Verified
Correct Answer:
Verified