Multiple Choice
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
A) The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B) The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
C) The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
D) The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
E) The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
Correct Answer:

Verified
Correct Answer:
Verified
Q530: The final project report should contain which
Q531: A new stakeholder has requested the status
Q532: Which of the following is the MOST
Q533: Which of the following activity sequencing techniques
Q534: A project manager creates a Pareto chart
Q535: A customer asks a project manager if
Q536: A project manager receives an initial project
Q537: In which of the following situations is
Q539: A PM notes a feature that was
Q540: A highly skilled project engineer will be