Solved

A Company Has Dictated Project Scope Changes but Has Stated

Question 284

Multiple Choice

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?


A) Quality
B) Regulations
C) Schedule
D) project team

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions