Multiple Choice
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?
A) Schedule
B) Milestone
C) Gate
D) Task
Correct Answer:

Verified
Correct Answer:
Verified