Multiple Choice
A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
A) Submit a change request.
B) Evaluate the impact of the change.
C) Get approval from the CCB.
D) Communicate the change to stakeholders.
Correct Answer:

Verified
Correct Answer:
Verified