Multiple Choice
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
A) Go over the meetings objectives and agenda.
B) Brief the team on which tasks have fallen behind schedule and where the project has slack.
C) Refer to the risk register to map the risks to issues and mitigation strategies.
D) Review the issue log with the project team and identify potential risks.
E) Review an Ishikawa diagram with the project team to determine possible causes and effects.
Correct Answer:

Verified
Correct Answer:
Verified
Q252: Which of the following are mutually binding
Q253: Which of the following statements are correct
Q254: A risk with minor impact has been
Q255: The following tasks are required to complete
Q256: The PM has requested that a project
Q258: Which of the following is the BEST
Q259: A project manager has an opportunity to
Q260: A project manager is not required to
Q261: A project manager is creating the monthly
Q262: A company has been trying to implement