New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables. Which of the following is the BEST way for the PM to validate the assessment?
A) Ask the team for estimates, and review the project schedule and budget.
B) Ask the team to review the product scope and validate its impact on the schedule and quality.
C) Ask the team for estimates, and review the cost management plan.
D) Ask the team to perform a SWOT analysis, and validate the assessment.
Correct Answer:

Verified
Correct Answer:
Verified
Q401: Given the following sprint: <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg" alt="Given
Q402: An audit, project change, task initiation/completion, gate
Q403: One of the tasks on a project's
Q404: The project manager is reviewing the earned
Q405: A project manager is archiving of project
Q407: Which of the following captures unforeseen activities
Q408: A team member has finalized a discussion
Q409: A customer has requested additional features for
Q410: Which of the following documents would a
Q411: Which of the following should be included