After SOW and Contract Approvals, the Project Manager Plans to Schedule

Question 414

Multiple Choice

After SOW and contract approvals, the project manager plans to schedule a meeting with the business analyst and several end users. The project manager's main objective in this meeting is to:


A) identify resources
B) baseline the schedule
C) create deliverables
D) define requirements

Correct Answer:

verifed

Verified