A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the project domain to be:
A) delegated
B) instructed
C) consulted
D) employed
Correct Answer:

Verified
Correct Answer: