Multiple Choice
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
A) Update the project charter to include the functional manager as a key stakeholder
B) Publish the project schedule to the functional manager
C) Review the communications plan to ensure proper involvement
D) Add the incident to the issue log and seek resolution
E) Ensure the functional manager is on the status report distribution list
Correct Answer:

Verified
Correct Answer:
Verified
Q502: A project manager is assigned a project
Q503: The Chief Executive Officer (CEO) has announced
Q504: Which of the following provides tools and
Q505: Which of the following is a team-building
Q506: A number of requirements, conflicts, and reworks
Q508: A team member has reported Task 3
Q509: While developing a project schedule, the project
Q510: Which of the following includes setting governance
Q511: A project schedule lists a resource as
Q512: Team members have reported that meetings are