Multiple Choice
During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird's patterns. Lobbyists would like the team to move the project down the road. Which of the following constraint and influencer types are involved in this scenario?
A) Environmental; resources
B) Environmental; stakeholders
C) Deliverables; resources
D) Deliverables; stakeholders