Multiple Choice
A technician is responsible for overseeing twelve remote offices. There was a report of a power outage at one of the remote offices the night before, and now one of the servers there has not rebooted even though it was shut down gracefully. The technician was forced to travel two hours just to turn the server on. Which of the following is the MOST cost effective way to prevent future travel?
A) Install a generator onsite.
B) Install a remote management card in the server.
C) Install an uninterruptible power supply (UPS) onsite.
D) Move the server to the main office.
Correct Answer:

Verified
Correct Answer:
Verified
Q198: A user cannot save a 2 GB
Q199: A server technician is trying to minimize
Q200: When setting up a new Linux server
Q201: A technician is tasked with building a
Q202: Which of the following must be configured
Q204: Which of the following ports should be
Q205: Payroll checks are not printing. A job
Q206: An administrator checks a server running a
Q207: Which of the following is the MOST
Q208: Which of the following plans describes the