Multiple Choice
A server that has been in production for a year needs to be patched. Management enforces a strict policy to be followed on all production servers. The policy stipulates the following for all change management: Changes must be reviewed and accepted by a change committee. Changes must be made on development/staging servers two weeks before being made on production servers. Changes must have install and uninstall steps in case of issues. Which of the following are the BEST reasons to have a change management plan in place? (Choose two.)
A) To keep track of software changes on servers
B) To minimize unapproved outages or downtime
C) To enforce all technical personnel do paperwork
D) To enable management to track hours worked.
E) To make sure servers never get rebooted.
Correct Answer:

Verified
Correct Answer:
Verified
Q332: An administrator is selecting a backup technique
Q333: A server technician has changed a hard
Q334: A server technician works in a small
Q335: A hardware compatibility list recommends striping with
Q336: Which of the following PKI elements will
Q338: After a migration to a new server,
Q339: A critical server has stopped responding in
Q340: A systems administrator is tasked to add
Q341: A technician is asked to make recommendations
Q342: When configuring networking on a VM, which