Multiple Choice
If the budgeted amount for fixed manufacturing overhead is less than the standard hours allowed for the actual output times the standard rate, the result is:
A) A favorable fixed overhead budget variance
B) An unfavorable fixed overhead budget variance
C) A favorable volume variance
D) An unfavorable volume variance