Operational Planning Must Be Completed by First-Line Managers Every ________

Question 59

Multiple Choice

Operational planning must be completed by first-line managers every ________, and tactical planning is done by middle management every


A) year; 2 to 10 years.
B) 6 to 24 months; 1 to 52 weeks.
C) 1 to 52 weeks; 6 to 24 months.
D) 1 to 12 weeks; year.
E) year, if necessary; 1 to 90 days.