Multiple Choice
One method of estimating project time is to use industry standard factors for each project phase. With this method, if the planning phase typically takes 15% of total project time, and a particular project requires three months for planning, then the remainder of the project will require _____.
A) 15 months
B) 20 months
C) 3.5 months
D) 4.5 months
E) 3 months
Correct Answer: